Demolition Week
Lots of removal and demolition this week with the deck & fence coming up and stored followed by knocking down the kitchen and digging up the dinning room to work on the drains.
- The new 'Crack House' chic front door (our neighbours description)
- Building work = Skip
- And deliveries
- Starting to remove the deck
- Deck removed and covered
- The rest of the garden covered and drain pipes delivered
- OK what's next...
- The dinning room ceiling
- No dinning room ceiling
- With the fire surround gone to it's new home time for the chimney breast to be removed
- Lee tidying up after the demolishion
- Time to find where the drains run
- And then replace part of the old ceramic pipes with plastic to make new connections
- Waste pipes for the shower room and kitchen
- The kitchen roof with the felt removed
- The kitchen roof with the plywood removed
- The kitchen roof with the joists removed
- The open air kitchen
- Kitchen with walls
- Kitchen - one wall removed
- Kitchen - two walls removed
- Kitchen with no walls
- 1st floor toilet temporarily removed to reposition soil stack